Berry Plastics

Skip Navigation LinksHOME > Polyken > Polyken Case Studies
 

Case studies:

Korea

Location:
The Young Heung Fossil Power Plant Project (Korea)
The Challenge:
To provide flexible pipe and fittings coating solutions to satisfy a variety of applications in a Fossil Power Plant.
The Young Heung Fossil Power Plant, state owned has approx 11,000 m² (118,404 sq ft) of pipe surface with straight pipe and fittings of in-plant pipelines for cooling water. Various kinds of diameters of pipe and fittings are from 1,800-2,800 mm (70-110”).
Our Solution:
Having selected a standard, KEPCO, and KOPEC then had to select a PE tape coating system supplier with a proven track record of compliance with AWWA C214. Again, after extensive evaluation of many systems, Polyken® Pipeline Coatings
were selected.

JR-004-Polyken-980-20-955-30-856-30-930-55-955-20.pdf